| width = "50%" | Description
 +
|-
 +
| 15-Sep
 +
| 2
 +
| Class (presentations)
 +
| listening to presentations
 +
|-
 +
| 15-Sep
 +
| 3
 +
| background research existing mailboxes
 +
| looked up what kind of (package) mailboxes are available today.
 +
|-
 +
| 17-Sep
 +
| 2
 +
| preparing Group Meeting + process requirements
 +
| making design requirements matrix.
 +
|-
 +
| 18-Sep
 +
| 3
 +
| group meeting
 +
| brain storm ideas, looking at requirements. dividing tasks
 +
|-
 +
| 20-sep
 +
| 3
 +
| working on wiki, package delivery, processing brainstorm ideas
 +
|}
 +
<br>
<br>
-
'''Total hours:''' hours
+
'''Total hours:''' 13 hours
<br>
<br>
 +
=week 4=
=week 4=

Revision as of 15:23, 25 September 2014

Go back to Personal Logs.

Contents

Week 1

Date Time Spent Task Description
01-Sep 2 1st Class Brainstorm Project Ideas
02-Sep 2 Research looked up what Amazon Prime air is trying to find more about prime air.
04-Sep 2 Group Meeting Discussed our topic and research tasks & presentation were divided
08-Sep 2 Lecture Listened to group presentations of their projects & approaches


Total hours: 8 hours

week 2

Date Time Spent Task Description
8-11-Sep 2 searching for sources working on the mindmap figuring out wiki searching for sources about regulations of flying with drones (in specific the ones amazon is using)
11-Sep 4 Group meeting defining topic further due to the lack of information we could find. looking at mindmap, discussing what to do.


Total hours: 6 hours

week 3

Date Time Spent Task Description
15-Sep 2 Class (presentations) listening to presentations
15-Sep 3 background research existing mailboxes looked up what kind of (package) mailboxes are available today.
17-Sep 2 preparing Group Meeting + process requirements making design requirements matrix.
18-Sep 3 group meeting brain storm ideas, looking at requirements. dividing tasks
20-sep 3 working on wiki, package delivery, processing brainstorm ideas



Total hours: 13 hours

week 4


Total hours: hours